Milestones

This page is the human-readable summary of every milestone and the work still open. It is a projection of the authoritative, machine-readable project-state.yaml: make docs-check fails when a milestone appears here under the wrong group, under a stale title, or with a checklist that disagrees with that file's open_items. Update the state file first; this page follows it.

The verified gate ceiling is Milestone 14 (289 cumulative gates). The parallel workstreams below advance their own gates independently but never move that ceiling; it advances only when Milestone 15 completes. Which gate belongs to which milestone is the milestone map; the authoritative acceptance criteria live in the engineering plan.

At a glance

State reviewed on 2026-09-28 against main at e55551fa, which production runs as release 20260928-202932-e55551f; Milestone 14's completion was recorded on 2026-10-09. With Milestone 32 authorized, twenty-two of thirty-three milestones are complete; ten were in progress and one was authorized but not started at that review. The independent reliability repair now begins Milestone 15 under ADR-0205. Milestone 32 has implemented components and registered gates; comparative quality and complete runtime/release evidence remain pending.

Milestone State What remains Who acts
15 Operational hardening In progress All sixteen gates; independent reliability repair under ADR-0205 Engineering, then owner
18 Email integration In progress Mailbox smokes; 1 open review finding Owner; engineering
21 Memory distillation In progress Final-head review; production formation@9 check; Sol/Astra study Engineering; owner
24 SMS In progress Physical-iPhone verification Owner
25 WhatsApp In progress Meta ceremony, live smoke Owner
26 Email experience In progress Private evaluations, cost calibration, two-account acceptance Owner with engineering
27 Bland calling In progress Dashboard and live checks; final-head review Owner; engineering
28 People In progress All 36 gates unbound; verification, evaluations, review Engineering; owner
30 Advisory approval In progress Threshold calibration and enforce decision; final-head review Owner; engineering
31 Email unsubscribe In progress Simulator journeys, mailbox smoke; final-head review Engineering; owner
32 Memory reconsolidation In progress Measured quality failures, remaining integrated gates and release evidence Engineering

Complete

  • Milestone 0 — Repository and engineering foundation
  • Milestone 1 — In-memory vertical slice
  • Milestone 2 — PostgreSQL persistence and durable worker
  • Milestone 3 — Model adapters (OpenAI, Anthropic, OpenAI-compatible) and normalized streaming
  • Milestone 4 — Policy, approvals, and complete tool lifecycle
  • Milestone 5 — HTTP API and SSE
  • Milestone 6 — Isolated execution and artifacts
  • Milestone 7 — Context budgeting and structured working state
  • Milestone 8 — Skills and MCP integration
  • Milestone 9 — Long-term memory and knowledge retrieval
  • Milestone 10 — Automatic memory, skills, public-web, and authenticated-browser tranches
  • Milestone 11 — Scheduled runs
  • Milestone 12 — Notifications and device identity — completed with production APNs delivery owner-verified on a physical iPhone.
  • Milestone 13 — General-purpose subagents and delegation — completed on 2026-08-27, when pull request 72 passed hosted CI and a clean CodeRabbit review on its final head; the delegating arm scored above the failed single-agent baseline. Recorded on 2026-09-28, moving the verified ceiling to Milestone 13.
  • Milestone 14 — Inbound surfaces and pairing — completed on 2026-10-07: the owner's production Telegram smoke passed on 2026-10-06, and pull request 153 shipped its one finding with hosted CI and a clean CodeRabbit review. Recorded on 2026-10-09, moving the verified ceiling to Milestone 14.
  • Milestone 16 — Memory evaluation and lifecycle — the first parallel workstream to complete; hosted review finished clean on 2026-08-23.
  • Milestone 17 — Memory read API and browser — the second completed parallel workstream; hosted review finished clean on 2026-08-24, followed by supplemental end-to-end PostgreSQL and native navigation coverage.
  • Milestone 19 — Conversational schedule creation — hosted CI and review finished clean on pull requests 64 and 66 (2026-08-25).
  • Milestone 20 — Calendar recurrence and conversational schedules — hosted CI and review finished clean on pull request 74 (2026-08-28).
  • Milestone 22 — Persona surface and curated belief promotion — hosted CI and review finished clean on pull request 82 (2026-09-01).
  • Milestone 23 — Conversational schedule lifecycle — hosted CI and review finished clean on pull requests 89 and 98 (2026-09-03 and 2026-09-06).
  • Milestone 29 — Chat thread folders — hosted CI and review finished clean on pull requests 118 and 127, including the ADR-0110 typed-judgment amendment, and the owner activated folders in production (2026-09-21).

Evidence for completed milestones lives in verification-history.yaml. Milestones 13, 19, 20, 22, 23, and 29 met their completion rules weeks before this page caught up; their status was recorded on 2026-09-28 from the pull requests' review and hosted-CI records.

In progress

Milestone 15 — Operational hardening

The independent ADR-0205 repair adds safe failure references, worker backoff, cleanup isolation and scoped reliability reporting. Focused failure-injection and PostgreSQL regressions pass; production delivery remains pending. All sixteen operational-hardening gates remain open, including off-host backups, restore rehearsals, watchdogs and independent outage alerts.

  • [ ] Complete all sixteen Milestone 15 gates and reviewed production delivery
  • [ ] Implement encrypted off-host backups and verify restore rehearsals
  • [ ] Complete host health probes and an independent outage alert channel
  • [ ] Verify firewall, SSH, proxy, rollback and worker watchdog hardening
  • [ ] Measure production reliability and explicitly activate reviewed monitoring

Milestone 25 — WhatsApp business surface

The optional WhatsApp Cloud API adapter now runs on the Milestone 14 surface seam: its loopback webhook verifies the handshake and raw-body signature, normalizes Meta message IDs into shared receipts, confines outbound calls to the Meta Graph origin, and enforces template-only delivery outside the twenty-four-hour window. All twelve gate.whatsapp.* entries resolve to live checks and pass locally. It shipped in pull request 104 with Milestone 14 and shares its review resolution and surface run budget. The WhatsApp integration runbook owns the remaining operator ceremony. Remaining:

  • [ ] Complete the owner Meta ceremony and obtain approval for the content-free utility template
  • [ ] Deploy and run the live-number webhook, pairing, reply, approval, window-boundary, and revocation smoke

Milestone 18 — First-class email integration

A parallel workstream providing one isolated triplet of least-privilege Gmail MCP servers per operator-managed account for read and triage, drafts and label mutation, and approval-gated sending. All seventeen gates and the full local repository check pass; ADR-0085 owns the four multi-account additions. The final head of pull request 73 passed hosted CI, GitGuardian, and CodeRabbit with every review thread resolved before merge (Glen review). The multi-account extension reached main in pull request 94, which merged with one CodeRabbit finding unresolved and still unfixed. Follow the Gmail integration runbook for the remaining owner-controlled work. Remaining:

  • [ ] Owner real-mailbox smoke covering bootstrap consent, scheduled triage, phone approval, and one approved send
  • [ ] Work-account bootstrap, production manifest activation, and work-only draft smoke
  • [ ] Resolve the CodeRabbit finding pull request 94 left open (a root-level --account-id never reaches bootstrap), then pass hosted CI and the CodeRabbit review loop for the multi-account extension

Milestone 21 — Adaptive memory distillation

A sixth parallel workstream making memory formation materially less timid. Its thirty-one gates cover integrated episodes, the fixed three-call prediction-error pipeline, direct and hypothesis recall, evidence-based forgetting, persistence, comparative activation evidence, the honesty of that evidence: a scorer that cannot be fooled, a seeded evaluation store, a fallback that never fabricates, verified coverage dispositions, and bounded segmentation, and the repaired provider-assisted formation@10 control with its explicit policy precedence (ADR-0086). ADR-0090 widens the existing source-grounding gate so authenticated communication channels can form bounded, attributed memories without upgrading correspondent content to owner speech. The local implementation, static and contract suites, strict documentation build, and Apple package tests pass locally; the fresh PostgreSQL 16 integration lane passed in hosted CI on pull request 90 (CircleCI build 2668); and the 2026-09-03 three-arm live production-tuple corpus under distillation-scorer@2 passed. The 2026-09-02 artifact was withdrawn because its scorer, corpus, empty store, and build reference could not support the numbers it carried; the replacement is bundled for immediate exact-tuple activation. On 2026-09-03 the deployed artifact was found bound to the pre-Milestone-24 policy version and was regenerated on the deployed tree; the bundle test now refuses that mismatch, and the starved formation@8 artifact is withdrawn in favor of formation@10. On 2026-09-04 an independent review reproduced eight release-blocking defects; each is fixed with a regression test (ADR-0087), the scorer advanced to distillation-scorer@5, and the formation@9 artifact evaluated under the old scorer is withdrawn, so formation@10 serves the production tuple until formation@9 is re-evaluated on the deploying tree. On 2026-09-09 the first run over the development corpus and the frozen holdout failed on hypothesis recall, precision, and paraphrase-bound direct recall; the defects it exposed are fixed and the scorer is distillation-scorer@6. A bounded prompt round on 2026-09-10 lifted holdout hypothesis recall to 0.800 and the development corpus to full direct recall, but the holdout still failed on direct recall and precision. The owner then set a recall-first bar (distillation-scorer@7, a 0.75 holdout precision floor) and gating over three pooled repeats; the run at 0e3ca2f passed and its formation@9 artifact is bundled. It reached main in pull request 104 and was first deployed by the next merge; the artifact stays bound to the unchanged shipped policy, but no production selection audit naming formation@9 has been recorded since. Remaining:

  • [ ] Run hosted CI and the CodeRabbit review loop on the final head
  • [ ] Promote the bundled formation@9 evidence to main through the CodeRabbit loop and verify the deploy selects formation@9 for the production tuple
  • [ ] Memory formation temporarily remains on GPT-5.6 Sol under ADR-0093; audit scorer semantics and compare Sol/Astra under controlled reasoning settings before changing the memory tuple with new activation evidence.

Milestone 24 — SMS through the owner's iPhone

A ninth parallel workstream. The DeviceChannel port with its push-wake adapter, capability-derived device.sms.send registration, the three device-authenticated routes, the SMS ingest path with its standing triage session, and the expiry sweep are implemented, all twelve registered gates pass locally, and the iOS client's SMS integration setting, compose-sheet send flow, "Forward Message to Veetbot" App Intent, and ingest forwarding are built with the owner capture ceremony documented (deployment.md). Remaining:

  • [ ] Owner end-to-end verification on a physical iPhone

Milestone 26 — Client modes and adaptive email experience

The owner approved the complete email experience and aggregate automatic-email budgets on 2026-09-11 under ADR-0092. Twenty-seven of its thirty-two registered gates now bind implemented backend and native acceptance checks; four private quality gates and the integrated release gate remain pending. No private quality or owner-smoke evidence is claimed. The milestone stays in progress and does not move the verified ceiling. Remaining:

  • [ ] Calibrate aggregate cost and performance with authorized representative mailbox work
  • [ ] Execute frozen private importance, reply relevance and writing-style evaluations with the owner
  • [ ] Pass private semantic precision, recall and usefulness evaluation before activating the exact policy tuple
  • [ ] Pass all thirty-two Milestone 26 gates and relevant local, PostgreSQL, native and private quality evaluations
  • [ ] Record authorized two-account real-mailbox acceptance and final-head hosted review and production delivery evidence
  • [ ] Deliver the independently verified expired-source drafting repair (ADR-0205)

Milestone 27 — Bland calling and public reception

Approved on 2026-09-11 under ADR-0097. Local implementation includes twelve executable offline gate bindings, PostgreSQL contract evidence and 289 passing Apple package tests. Calling has been active in production since 2026-09-17. Live inbound calls and one owner-approved outbound call are retained, readable from Chat and announced to every device. Reaching that point took two fixes: ADR-0105's tool-definition budget and the missing call_finished lock-screen alert. Bland's signed post-call webhook has been verified in production against the raw bytes. Every pull request that carried calling to main passed hosted CI and a clean review; the final-head review waits for the two pending gates, gate.call.admission_bounds and gate.call.live_release, to be bound.

  • [ ] Verify provider-side admission controls and account-level memory or persona attachments in the Bland dashboard
  • [ ] Live approval denial, no-answer, post-dispatch cancellation and owner deletion checks
  • [ ] Exact-head hosted CI and explicitly authorized CodeRabbit review evidence

Milestone 28 — People and relationship memory

Thirty-six gates; independent workstream under ADR-0100.

ADR-0101 makes the complete implemented Milestone 28 People experience available by default. Quality measurements remain open evidence work, without gating runtime functionality or release. None of the thirty-six gate.people.* registry entries is bound to an executable check yet; every one still points at the pending check. Production delivery still follows exact-head CI/review.

  • [ ] Bind each of the thirty-six gate.people.* registry entries to an executable check; every one still points at the pending check
  • [ ] Review complete temporal/source-erasure gate coverage and worst-case initial-fence latency
  • [ ] Finish native accessibility, load/contention and signed restore verification
  • [ ] Independently reviewed labels, version-bound quality and private owner evaluation evidence
  • [ ] Private quality evaluation of the generated correspondence summaries that ADR-0126 activated ahead of it
  • [ ] Exact-head hosted CI and explicitly authorized review and production delivery evidence

Milestone 30 — Advisory approval layer

Five gates; independent workstream under ADR-0111, the restrictive-only half of roadmap item B8. An optional advisor behind a port can only escalate an allowed web search, page fetch or browser navigation to an approval; it never denies, abstains on any failure, and is consulted once per invocation. The port, the composite engine, the judgment-backed advisor and the pipeline's recovery policy are implemented with all five gates bound to executable checks, and reached main in pull request 127 with a clean review. Observing is an environment flag that moves no policy version; enforcing is the profile value and does, and the shipped profile keeps it disabled.

  • [ ] Calibrate the advisor's thresholds while observing, then decide whether to enforce
  • [ ] Exact-head hosted CI and explicitly authorized review and production delivery evidence

Milestone 31 — Email unsubscribe assistance

Twenty-three gates; independent workstream under ADR-0112, extended by ADR-0165. A header-derived census of bulk senders, the authenticated one-click unsubscribe request to a server-derived destination through a dedicated public-HTTPS transport, and Report spam, mailto: and sender-cleanup fallbacks, each behind the owner's tap; and a suspected-spam flag that never touches Gmail, with thread-level Report spam and Not spam. Nineteen gates bind passing checks. The milestone reached main in pull request 131 with a clean review, and its flag was switched on in production by 2026-09-21, ahead of the owner's real-mailbox smoke.

  • [ ] Pass the five native Subscriptions journeys (added 2026-09-28 and passing locally on the iPhone and iPad simulators) in the hosted Mac, iPhone and iPad UI lanes
  • [ ] Show the Subscriptions detail beside its list on regular-width iPad as email-unsubscribe.md requires; the iPad sheet is a 580-point compact-width form sheet, so the detail pushes as on iPhone
  • [ ] Pass the two native suspected-spam journeys (added 2026-10-08 and passing locally on the Mac and the iPhone and iPad simulators) in the hosted Mac, iPhone and iPad UI lanes
  • [ ] Owner-authorized real-mailbox smoke on both accounts covering one-click, mailto, sender and thread spam each with Not spam, and cleanup
  • [ ] Exact-head hosted CI and explicitly authorized review and production delivery evidence

Milestone 32 — Memory reconsolidation (dreaming)

The detailed design declares twenty-four registered gates. Both stores implement bounded inventory, leases/spend, merge, summary, grounded connection and conflict operations, source invalidation/erasure, owner controls and gated background composition. The Synthesis browser exposes supporting originals, uncertainty, conflicts and previewed merge undo. Shared contracts, PostgreSQL RLS/migration checks, Apple package tests and iPhone/iPad journeys cover these components; the complete runtime/release gates remain pending.

Two answer-bearing original controls and full three-arm comparisons are retained under evals/observations/memory-reconsolidation/. Both failed the unchanged quality gate. The second run preserved every fact and had zero false merges, but its answer lift was only 1/36 per split, merge answers regressed and no hypothesis matched the scorer's exact reference wording. The owner approved ADR-0170 on 2026-10-08; its offline equivalence-review contract is implemented. The third comparison bound that contract before measurement. The owner judged all fifteen candidates: ten equivalent and five not equivalent. Precision is 75% on development and 57.14% on holdout, below the unchanged 80% floor; recall passes both splits. Every fact is preserved with no false merges, but answer lift and development merge-answer nonregression still fail. Review artifacts and the recomputed assessment are in evals/observations/memory-reconsolidation/20261008-owner-review-v2/. Unattended processing stays off.

The ADR-0171 isolated owner-data experiment completed on 2026-10-09, and the owner judged its accepted related-memory summary useful. This completes that review; legacy bank replay and the comparative quality failures remain unresolved.

The October 9 diagnostic comparison records 14/18/14 development and 17/17/19 holdout answers out of 36 for original/merge/connections. Merge-answer nonregression passes, but answer lift remains below ten percentage points. Eleven new hypotheses remain unverified; earlier judgments and failures remain unchanged. The design records the repairs and measured limits.

ADR-0174 owner-reviewed production mode is live on d053d1d9: daily proposals, the private review page and individually approved application are enabled across all eight application roles. macOS and iPhone/iPad journeys, final-code review, hosted verification and application/docs/site/TestFlight delivery passed. The first daily batch deferred without proposals or provider calls. This supervised path requires no further blinded packet and does not satisfy unattended quality gates.

  • [ ] Resolve precision and answer-lift failures without repeating completed owner reviews; new hypothesis quality remains unverified under ADR-0170, and release-tuple proof is still required
  • [ ] Complete the once/dry-run operator controls and bind each remaining complete runtime gate to integrated evidence
  • [ ] Publish matching upstream, comparative and exact-revision release evidence before unattended production activation

Milestone 33 — General memory search and recall

ADR-0179 adds a version-bound local semantic index and experimental shared recall, with correction/erasure fences and exact pgvector search. ADR-0180 adds bounded provider admission, durable spending and resumable indexing slices. ADR-0181 adds explicit query preparation and a bounded local cache sharing the indexing budget. ADR-0182 binds shared preparation and recall to saved run/checkpoint state and current query policy. ADR-0183 refreshes current evidence on every production context assembly. ADR-0185 adds exact-version release-bundle validation and recomputes quality/budget admission. Source indexing has default-off maintenance composition and configuration bound to reviewed release dependencies (ADR-0187). Offline model verification, restricted local query authority and shared run preparation are implemented (ADR-0188), alongside governed source recovery (ADR-0189), durable preparation budgets (ADR-0190) and a separately admitted relevance reranker (ADR-0191). The runtime evaluator separates stored atoms from recovered source evidence (ADR-0192), and its PostgreSQL mode exercises actual workers and reader authority. The owner approved the 400-scenario corpus on 2026-10-13; difficult-failure review remains required. Current People narrowing has shared PostgreSQL coverage; a six-arm task-context comparison retains all 120 development observations. Reader-planned search answers 16/20, with four failures caused by guessed hard type filters. ADR-0198 replaces that model-facing argument with soft relevance hints while preserving explicit legacy filters. Historical semantic parity, confirmatory configuration binding and reviewed release evidence remain open.

Authorized on 2026-10-11 by ADR-0178, with twelve gates in the design. The staged implementation is in progress; optional channels remain evidence-gated.

  • [ ] Complete the staged implementation and comparative activation evidence
  • [ ] Complete the authorized dev-to-main PR review, hosted CI and production delivery after plan completion

Outside a milestone

Open work that no active milestone owns: owner-only steps of non-milestone ADRs, and specification-versus-code gaps found in completed milestones. It mirrors open_items_outside_milestones in project-state.yaml.

  • [ ] Owner: install a macOS TestFlight build carrying ADR-0127 to ADR-0130 (merge a9b81420 or later) on every Mac
  • [ ] Owner: confirm production AUTH_SCOPES contains browser.profile.read, browser.profile.write, browser.grant.read and browser.grant.write
  • [ ] Owner: production acceptance of device sign-in (ADR-0128 V1, V3 and V4; V2 once the iOS build ships)
  • [ ] Owner: once a client build that decodes approve_for_task runs on every device, set BROWSER_TASK_GRANT_SCOPES=https://www.duolingo.com/lesson and BROWSER_TASK_GRANTS_ENABLED=1 for the API and workers
  • [ ] Owner: production acceptance of the task grant (ADR-0129 Validation): one approval runs a lesson while the banner counts actions and minutes; Stop brings the card back; an action outside the lesson, such as a payment or settings control, still asks and says why; activity rows the grant authorized show "Allowed by task permission" and what was clicked or typed. Then measure the budget of the first lesson in a new bound chat (ADR-0130)
  • [ ] Owner: keep BROWSER_PROFILE_DEVICE_SIGN_IN_ENABLED unset or true in production; to turn device sign-in off, set it to false in /etc/veetbot/veetbot.env and recreate the browser-profile-service container with the block in docs/deployment.md (a restart keeps the old value)
  • [ ] Tool system: the circuit-breaker section of tool-system.md specifies one counter keyed on name, arguments hash, outcome and reason, but runtime/loop.py keeps separate identical-denial and identical-call counters; change the code or propose an ADR that accepts two (found during ADR-0130)
  • [ ] Command line: engineering-plan.md Section 17 and bootstrap-and-composition.md require agent chat, arriving at Milestone 3, but the CLI registers no chat command although Milestone 3 is complete; implement it or propose an ADR that removes it (found in the 2026-09-28 documentation audit)
  • [ ] HTTP API: event-log-and-persistence.md and ADR-0032 decision 9 require POST /v1/runs/{run_id}/export, but no such route is mounted and only agent run export exists; mount it or propose an ADR that drops it (found in the 2026-09-28 documentation audit)
  • [ ] Owner: accept or reject ADR-0104, ADR-0105, ADR-0106, ADR-0107, ADR-0114, ADR-0135, ADR-0137 and ADR-0138, which are still Proposed although their mechanisms are implemented, specified and on main
  • [ ] Owner: accept or reject ADR-0146, which is Proposed and implemented: a hosted browser launch repeats the Playwright disabled-feature list, gives push messaging a check-in address it cannot fetch, and leaves one account request to accounts.google.com on
  • [ ] Owner decision: the hardline protected_host_path rule blocks .git/config only at the workspace root, so sub/.git/config is not blocked, while .env and ~/.ssh already match at any depth; decide whether it should, knowing that a change to the matcher in policy/hardline.py leaves policy_version unchanged but an edit to hardline.yaml moves it and unbinds the memory-formation release evidence (found in the 2026-09-28 test audit)

The earlier item asking the owner to confirm the ADR-0127 to ADR-0130 deploy is closed: after the owner reran the workflow, deploy-app and deploy-nginx succeeded on merge a9b81420 (outside_milestone_evidence in the state file).

Authorized

No authorized milestone remains unstarted. Milestone 15 has begun its independent reliability repair; its remaining gates and backup tranche remain open.

Deferred

Nothing on the engineering plan's roadmap beyond Milestone 15 is authorized until the owner says so and a specification with gates exists for it. That roadmap holds, among its items: tenant activation of self-authored skills (B1), dynamic model routing and a second provider adapter (B2), Slack and email inbound surfaces (B3), email and webhook notification transports (B4), scheduling residue such as cron, interval multipliers, and dependency graphs (B5), the memory residue after Milestone 33 — an external memory provider and a learned memory policy (B6) — presence routing and hand-off (the B7 residue after Milestone 24), standing approval grants (B8), the trajectory-to-fine-tuning loop (B9), S3-compatible artifact storage (B10), calendar integration and the other B11 surfaces beyond email, and multi-tenant billing and quotas (B12), and the WhatsApp linked-device bridge (B13).

Work each milestone explicitly set aside is recorded as that milestone's deferred_scope in project-state.yaml; a deferred item re-enters only through a new authorization and, where the change is architectural, an ADR.